Lifting Projects UK 2nd Week (TBM-Mary) Removal
The Lifting Projects UK team are now in their 2nd week of the removal of the Tunnel Boring machine (TBM-Mary) at North Woolwich Cross Rail Site for Hochtief Murphy Joint Venture.
The tunnel-boring machine has now been fully removed from the portal base and transported from site. The team are now concentrating on pulling the gantries/bridge section into position for dismantling with the crane. All works are going to plan and the team are still set to complete the removal on schedule if not earlier.